Site Updates as on June 14th, 2018

Warehouse in progress

Organic Fertilizer- Fertimine being applied to the germinating crops

Open surface water storage tank being again dug up before stones & concrete is used

Site Pictures as on May 30th, 2018


Lawn with flower edges being prepared in front of Site Office

One of the two Deep Trenches  for HDPE mainlines  from the overhead tank to the field being dug up, Length – Approx. 1.75 kms.

Mainline trench being connected to the second main line trench at a distance of approx. 600 M